California High-Speed Rail Reaches 66 Structures Along First 119 Miles
California High-Speed Rail has completed four more structures in Kings and Tulare counties, bringing the total to 66 along the first 119 miles of Central Valley construction. The California High-Speed Rail Authority announced the completion of the State Route 43 Curved Bridge, Cross Creek Viaduct, Tule River Viaduct and Avenue 136 Underpass on October 7.

The milestone represents tangible civil-engineering progress, but not the completion of passenger rail service. These bridges, viaducts and grade separations are enabling works designed to carry future tracks across roads, waterways and freight infrastructure or move road traffic over the railway. They still must be connected with track, power, signaling and other systems before trains can operate, and their completion does not resolve the program’s broader statewide funding and delivery gap.
The four projects illustrate why counting structures provides useful, but incomplete, information about railway readiness. A high-speed line needs a continuous, controlled corridor without conventional road crossings. Building that corridor requires individual structures tailored to obstacles that range from two-lane roads to rivers and existing railway lines.
Four structures serve different crossing functions
The 660-foot State Route 43 Curved Bridge, located north of Corcoran, is a grade separation that will carry vehicle traffic over the future high-speed tracks. It measures 45 feet wide and reaches 60 feet at its highest point. Moving road traffic above the rail alignment eliminates the need for vehicles and trains to cross at the same level.
Nearby, the Cross Creek Viaduct extends more than 2,500 feet and is designed to carry trains over a waterway. It incorporates 222 California Wide Flange girders manufactured in Hanford by the Dragados-Flatiron Joint Venture. That local girder production is part of the less visible industrial work behind the completed concrete corridor.
The largest of the four additions is the 3,573-foot Tule River Viaduct. It will carry trains over State Route 43, the Tule River and existing freight tracks, combining several crossing requirements in one structure. Its construction uses 38 tub girders and 264 California Wide Flange girders.
Immediately south of that viaduct, the 55-foot Avenue 136 Underpass will carry the future railway above two-way road traffic. Although much shorter than the two viaducts, it performs the same fundamental systems function: separating highway and railway movements so each can operate without a level crossing.
Concrete progress precedes railway integration
Nearly 90 miles of guideway have now been completed, while another 30 structures remain under construction across Madera, Fresno, Kings and Tulare counties. Those figures show that work is advancing across a substantial portion of the Central Valley corridor, but completed guideway is not equivalent to an operational railway.
Civil works establish the physical path and carry the loads. Passenger service also depends on a continuous track system and the integration of traction power, train control, communications and safety systems. Each element must work across the corridor rather than only at individual completed sites. The relevant operational milestone therefore comes when separate construction packages become a connected railway capable of supporting trains, not simply when another bridge opens to road traffic or a viaduct reaches structural completion.
The Authority estimates that the four newly completed structures will generate $466 million in safety benefits over 30 years. Its projections attribute about 670 prevented crashes to Kings County grade separations and approximately 1,604 to the Tulare County works during that period. These are forecasts produced by the Authority, not independently established outcomes, and the eventual benefit will depend on how the completed crossings and surrounding transportation network are used.
Even before high-speed trains arrive, some grade separations can change local road layouts and remove conflicts with existing infrastructure. Their longer-term value, however, is tied to completion of the Merced-to-Bakersfield rail corridor they are being built to support.
With 66 structures finished and 30 more under construction, California has moved beyond isolated early works and assembled a growing physical corridor. The next consequential measure will be how quickly that concrete and steel can be joined by the track and railway systems needed to turn nearly 90 miles of guideway into usable passenger infrastructure.