Air Force One Faces $73.3 Million Communications Replacement Before 2028 Delivery
The two new Air Force One aircraft may reach their planned delivery dates with communications equipment already at the edge of obsolescence. An installed Mission Communication System must be removed and replaced at an estimated cost of $73.3 million because its current baseline is not considered viable beyond 2028 the same year the first aircraft is now expected to arrive.

A U.S. government program report released August 3 attributes that limited service horizon to cybersecurity and obsolescence concerns. Only about half of the estimated replacement funding has reportedly been approved and allocated. The direct operational issue is not simply having older electronics aboard: unresolved risk could prevent authorization to connect and operate on national-security systems required for presidential communications.
That makes the replacement a prerequisite for the aircraft’s mission rather than an optional technology refresh. It also illustrates a recurring problem in long aircraft-conversion programs: electronic equipment continues aging while structural modification, cabin integration and certification consume years.
A communications replacement reaches beyond the equipment rack
The VC-25B program involves converting two Boeing 747-8 aircraft into presidential transports. On an ordinary aircraft, replacing communications hardware can still require changes to power, cooling, wiring, antennas, software and operating documentation. On this heavily customized platform, the work also has to fit within a cabin and electrical architecture that remains under development.
The government report says interior-design maturity continues to lag because of technical and certification issues. Those delays have affected wiring design, fabrication and structural modifications, prompting changes in aircraft sections where work was already underway. The original presidential-interior contractor, GDC Technics, was replaced in 2021, adding another transition to a program whose systems must be integrated rather than installed independently.
This coupling is what turns the $73.3 million communications estimate into a schedule concern. Removing installed equipment can reopen completed work, while its replacement must be incorporated into the configuration used for ground tests, flight tests and military certification. A late design change therefore consumes more than installation labor; it can alter test plans and require engineers to demonstrate that connected systems still meet their requirements.
Certification cannot wait for every design problem in sequence
Boeing and the Air Force have agreed to move from Federal Aviation Administration certification to an equivalent military certification process. That changes the certification framework, but it does not eliminate the need to substantiate aircraft safety and mission performance. The program must still close design work, establish a controlled configuration and complete testing with representative systems installed.
Other unresolved hardware shows why that sequence remains vulnerable. Cabin-window supplier GKN has reportedly struggled with demanding manufacturing criteria, including defect-free subcomponents and controls intended to prevent particles from entering window assemblies. Delayed windows can hold up pressurization tests, interior installation and later ground and flight testing.
The cockpit windshields present a different supply-chain constraint. The original supplier ceased trading, no spare commercial 747-8 windshields are available, and replacement supplier PPG must develop a compatible windshield. Its design had not yet received certification as of the report. These are not interchangeable catalog parts that can simply be taken from a large active production pool.
Structural work is also unfinished. Cracks found in fuselage stringers require repairs, with 95 repairs or installations outstanding on the first aircraft and 142 on the second at the report date. Stringers run lengthwise along the fuselage and carry structural loads, so closing that work is part of establishing an aircraft configuration ready for subsequent installation and testing.
The 2028 target has little room for additional disruption
The Air Force is working toward delivery of the first VC-25B in 2028 and the second in 2029. Unexpected modification work or longer-than-planned testing could threaten both dates. Boeing, which recently added production and certification resources, recorded another $280 million program loss in the second quarter of 2026.
That corporate charge is separate from the $73.3 million communications-replacement estimate, but both reflect the cost of protecting a schedule after designs, suppliers and installed technology have changed. Budget oversight also continues through the fiscal 2027 process, whose broader defense appropriations framework is available in the House committee report.
Until the replacements can meet the full presidential mission, the Air Force plans to keep its two approximately 30-year-old VC-25A aircraft available and mission-ready. The central constraint is now clear: every additional month spent completing the new aircraft also demands more support for the old fleet, while giving installed electronics more time to age before the VC-25Bs ever enter service.
By David Whitaker — Associate editor for AMI’s aerospace and drone systems desk, translating flight systems, aircraft programs, spaceflight, and UAV developments into accessible technical stories.