Ofgem Fees Could Push Some UK Rapid Charging Above £1 Per Kilowatt-Hour
A rapid electric-vehicle charger needs a large grid connection whether it serves a steady queue of cars or sits idle for much of the day. Under the UK’s current network-charging structure, that connection size can create a substantial fixed bill before the operator sells a single kilowatt-hour.

That mismatch between electrical capacity and customer use is behind a warning from EV newsletter The Fast Charge and charging operator Zest. Their 2026 report projects that fixed network fees could force some UK public rapid chargers above £1 per kilowatt-hour in 2027, with drivers unable to charge at home particularly exposed.
The report calculates that the average fixed network charge for a standard rapid charger rose from £61.47 a week in 2021 to £440 in 2026 an increase of more than 600%. It expects the charge to rise by more than another £100 per charger per week in 2027. Some operators may need to set retail prices above £1 per kilowatt-hour to make a profit, while others could struggle to remain in business, it warns.
High power creates a fixed-cost problem
Rapid charging depends on delivering substantial electrical power over a short period. The grid connection therefore has to be sized for the charger’s peak requirement, even if the site reaches that peak only occasionally. A charger cannot compensate for an undersized connection simply by operating more slowly without giving up the rapid service it was installed to provide.
Ofgem’s 2022 changes shifted certain network costs away from charges linked primarily to electricity consumption and toward fixed fees based on connection size. Earlier guidance on the regulator’s network-charging proposals explained that residual charges recover costs such as maintaining existing wires, substations and other infrastructure. The charging guide also described Ofgem’s objective as distributing those fixed costs more fairly among network users.
For rapid-charging operators, however, connection size and energy sales can diverge sharply. A well-used motorway charger can spread its weekly network bill across many sessions. A newer site, a rural location or a charger installed ahead of expected demand has fewer transactions over which to recover the same connection-related expense.
At a £440 weekly fixed charge, a charger incurs nearly £23,000 a year before accounting for purchased electricity, equipment, maintenance, property, payment processing or other operating costs. If the projected 2027 increase exceeds £100 a week, the additional fixed burden alone would be more than £5,200 annually per charger. These figures do not mean every rapid charger will cross £1 per kilowatt-hour: utilization, connection size and the operator’s wider cost structure determine the retail result.
The access burden falls unevenly
The pricing consequence is most acute for motorists without driveways or other home-charging access. A household charger can draw power at a lower rate over many hours, while a public rapid charger is engineered around short stops and much higher power. Drivers dependent on public infrastructure cannot readily substitute the generally cheaper home-charging model.
The same mechanism also affects network expansion. Zest says the fixed-cost burden is increasing prices and causing some prospective charging projects to be delayed or abandoned. This creates a difficult development cycle: a new location may need time to attract regular users, but its connection-sized fees begin before demand reaches a level capable of supporting them.
Shifting charges back toward measured consumption could ease pressure on lightly used sites, as the report’s authors propose, but it would not eliminate the underlying network costs. More usage-based recovery would transfer some risk away from new charging locations and redistribute it among electricity users. Fixed charges provide predictable recovery for infrastructure that must remain available regardless of daily consumption; the policy issue is how much of that cost should follow reserved capacity and how much should follow actual energy use.
Ofgem is considering whether the rules need changing
An independent government review described the effect of the changes on public-charging operators as a “severe impact” and called for urgent action. Freedom of Information documents also showed that Ofgem told Treasury officials in October 2025 that the framework was producing a “high cost per customer” and an “unproductive cycle” for charging operators.
Ofgem says fixed costs ultimately have to be recovered fairly and efficiently, and it is considering the independent review, including whether changes are needed. Any revision will have to balance cost recovery across the electricity system against a distinctive engineering feature of rapid charging: sites require their high-capacity connections from day one, but the traffic needed to pay for them may take years to arrive.