Sulzer Will Replace Petrocedeño’s Damaged Tower to Restore Heavy-Oil Processing Capacity
Swiss engineering company Sulzer has been contracted to manufacture and install a new atmospheric crude-distillation tower at the Petrocedeño upgrader in Venezuela. North American Blue Energy Partners, or NABEP, chose complete replacement over temporary repairs because the existing tower was severely damaged in an explosion and fire in November 2025.

The decision addresses a major constraint in a plant built to convert extra-heavy Orinoco Belt crude into a lighter product that can be transported and processed by conventional refineries. NABEP identifies replacement of the damaged tower as an important requirement for returning the upgrader to full operating capacity. A verified installation or commissioning date has not been established.
Sulzer’s work extends beyond the failed tower. The agreement also covers new internal separation equipment for Petrocedeño’s existing preflash and vacuum towers, along with commissioning and maintenance services. Treating the three towers as connected parts of the processing train is intended to improve separation, throughput, operating efficiency and safety across the facility rather than merely restore one damaged vessel.
Why NABEP selected full replacement
An atmospheric distillation tower is central to the first major separation stage in crude processing. Its loss can therefore restrict more than a single piece of equipment: downstream stages depend on receiving material separated under the required process conditions. At Petrocedeño, that constraint is especially consequential because the incoming crude is extra-heavy and must be upgraded before it can move through conventional refining channels.
NABEP chief executive Alejandro Betancourt said the company rejected a temporary repair of the remaining structure and instead selected a new tower designed to stringent safety standards. That choice trades the potentially faster path of patching existing equipment for a more extensive reconstruction intended to provide a durable operating asset.
The scope also suggests that restoring the original arrangement alone is not the project’s objective. New internals for the preflash and vacuum towers are meant to improve how crude fractions are separated through successive parts of the train. NABEP expects the combined work to increase processed volume and raise the share of higher-value products, although it has not provided a quantified throughput gain for the Sulzer project.
Three linked towers shape the recovery
The preflash tower, atmospheric tower and vacuum tower serve different but connected separation duties. In broad terms, the preflash stage removes selected lighter material before the main atmospheric separation, while vacuum processing allows heavier fractions to be separated under reduced pressure. Performance at one stage affects the feed conditions and workload encountered by the next.
That systems relationship explains why renovating the two surviving towers can matter almost as much as replacing the visibly damaged one. Installing a new atmospheric tower without addressing worn or outdated separation components elsewhere could leave bottlenecks in place. Coordinating the tower replacement, internal-component upgrades, commissioning and maintenance gives Sulzer responsibility across several interfaces that must work together when the train is returned to service.
Petrocedeño operates at the José industrial complex near Barcelona in Venezuela’s Anzoátegui state and processes extra-heavy crude from the Zuata 2 area. The facility’s purpose makes dependable separation hardware fundamental to both output and product quality: the plant must turn difficult feedstock into lighter crude suitable for transport and further refining.
The remaining uncertainty is schedule. A stated 2025 replacement date conflicts with the November 2025 incident and with other reported company developments during 2026, so it cannot serve as a reliable commissioning milestone. Until NABEP or Sulzer confirms an installation sequence, the project’s engineering scope is clearer than its delivery calendar. Petrocedeño’s return to full processing capacity now depends on completing a new main tower and integrating it with two renovated separation stages not on temporarily patching the damaged structure.