LAX People Mover May Miss Next Super Bowl With March 2027 Opening
The LAX Automated People Mover is caught between two competing explanations for why it still cannot carry passengers. Contractor LINXS points to an unresolved solar-power arrangement involving the airport and the Los Angeles Department of Water and Power. Los Angeles International Airport says the principal constraint is LINXS’ failure to complete required demonstrations of the train’s reliability and safety.

The immediate consequence is another potential schedule slip. LINXS’ latest monthly update projects a public opening on March 8, 2027, which would leave travelers without the planned airport rail connection through the next Super Bowl in Los Angeles. LAX has not confirmed that opening date, and LINXS declined to comment on the latest projection.
The disagreement is more than a dispute over who caused a delay. It concerns which unfinished task controls the schedule: an administrative and electrical-integration agreement, or the system-level testing needed before passengers can board. Until the parties align on that critical path, a date in a contractor schedule is not the same as an approved entry into service.
Testing remains the airport’s stated constraint
“The primary factor in the delay is LINXS’ inability to complete required system demonstration testing to ensure the reliability and safety of the train,” LAX said in a statement disputing the contractor’s account.
The commissioning requirement helps explain why a system described as 99% complete can remain unavailable. Before opening, the train must complete 30 consecutive days of testing without substantial issues, followed by approval from the airport and an outside assessor. A significant interruption can restart that test period, making the final percentage of physical construction a poor measure of readiness for passenger service.
That distinction is especially important after electrical problems during September testing. Four arc-flash incidents damaged the power rail and guide beam, according to project-monitoring information detailed by Engineering News-Record. Airport officials said LINXS repaired the damage and testing resumed. No final cause for those incidents has been provided.
Resuming train movement, however, does not complete the broader demonstration program. An automated railway must show that its vehicles, power supply, guideway, controls, fire systems and operating procedures function together reliably across the required test window. The airport’s position is that this integrated demonstration not the solar agreement is holding back passenger service.
LINXS identifies the solar arrangement as a schedule blocker
LINXS argues that LAX and the Department of Water and Power have not completed an agreement covering solar energy for the system. The planned rooftop installation at the maintenance and storage facility was described as supplying 40% of that facility’s energy and 7% of the People Mover’s overall electricity requirements.
The relatively modest systemwide share does not by itself establish whether the agreement is on the project’s opening critical path. The contractual question is whether solar connectivity and the associated approvals are prerequisites for acceptance, or whether that work can be separated from launching passenger operations. Previous reporting indicates the airport moved to revise the project scope so the solar installation would not prevent the train from opening, while LINXS has maintained that the unsigned arrangement continues to affect its schedule.
This is a systems-integration and accountability problem as much as an energy issue. If the solar arrangement is a contractual prerequisite, an unsigned interdepartmental agreement can constrain a multibillion-dollar transportation system even when most construction is finished. If it is not required for initial service, the remaining reliability and safety demonstrations become the more immediate gate. The parties have not reached a common public account of that dependency.
The conflict has expanded beyond engineering closeout. LINXS sued the city during the summer, alleging several problems including a refusal to extend project deadlines. Its monthly report also alleged that a person suspected of being an airport employee entered the construction site without authorization and removed a key cylinder from the Fire Command Center. LAX dismissed the contractor’s claims in its response.
Los Angeles City Councilmember Traci Park has requested information on the city’s available contractual remedies, potentially including termination. She has not endorsed terminating the contract, and the request does not represent an active termination decision. A credit-rating downgrade has nevertheless underscored the consequences of missing contractual milestones; Fitch Ratings lowered the project debt to B- as completion uncertainty continued.
The 2.25-mile automated line is intended to connect LAX terminals with parking, the consolidated rental-car facility, the LAX/Metro Transit Center and a ride-hail area. It was originally expected to open in 2023 and is now more than $1 billion beyond its original construction budget. Its next meaningful milestone is not another projected date, but completion of an uninterrupted reliability run and agreement on which remaining contractual approvals are actually required before passengers can board.